Suffered from power outage
Television sets, refrigerators, boilers and other electronic appliances were out of the households in the Hovuni and Mayisyan districts after a power outage on the night of October 13. The village heads appealed to the electronic network in the region with a list of injured families and demanded compensation. Nearly 140 families suffered losses.
At around 3 a.m. on October 13, some residents of the Mayisyan district noticed waves of electricity and sensed the smell of smoke in the rooms. They turned off all electronic appliances from the sockets, but in the morning they saw that it was too late. Hripsime Arakelyan wanted to entertain her grandchild with a new cartoon DVD, but that didn't take too long.
Hovhannes Sahakyan had purchased an expensive television set that didn't work in the morning. "I bought it seven months ago. I took it to the store and they told me that it was due to the power outage and they were not obliged to repair it," says Sahakyan.
The computer room at the Mayisyan middle school suffered the most. The room is equipped with 9 computers serving the students and the administration. Overall, nearly 50 families suffered from the power outage.
There were power shifts in Hovuni with a total of 90 families as well.
Mrs. Angela and her husband are no longer able to watch television. "My husband really wants to watch television to find out what's going on. My grandchild went and brought this small television set," says Mrs. Angela. Nearly 70 television sets and other appliances in 136 households were damaged. Head of the Hovuni district Telman Mirijanyan is aware of the issue and has appealed to the corresponding bodies who assured that the residents will be compensated for the damages.
Chief engineer of the "Kars" branch of the Armenian Electronic Networks CJSC Grigor Martirosyan affirmed that the company would fulfill all its commitments and would restore all malfunctioning technical appliances.
According to villagers, the rise of pressure was due to the birds resting on the electricity wires. But chief engineer of the "Kars" branch of Armenian Electronic Networks Grigor Martirosyan says that it was due to the worker controlling the amount of pressure.
A commission has been created and sent to the injured districts to estimate the number of electronic appliances damaged as a result of the power outage on October 13 and find out the necessary amount for compensation.
Tsaig